Periodic Structural Inspection — BCA's mandatory health check for older buildings.

Under the Building Control Act, every non-residential building must be inspected every 5 years and every residential building every 10 years. CVC Engineers performs the inspection, files the structural condition report with BCA, and walks owners through any rectification works that arise.

Get a PSI quote

What PSI actually involves.

PSI is a physical inspection of the structural condition of a building by a registered Professional Engineer (Civil). The PE submits a structural condition report to BCA confirming the building is safe to occupy — or flagging defects that require attention.

PSI is mandated under Section 28 of the Building Control Act, with detailed inspection requirements set out in BCA's PSI Inspection Manual. Inspection frequency:

  • Non-residential buildings — every 5 years (commercial, industrial, hospitality, education, healthcare)
  • Residential buildings — every 10 years (HDB blocks, condos, landed)
  • Heritage / conservation buildings — typically every 5 years regardless of use
  • Buildings flagged at previous PSI — frequency may be shortened if defects were noted

The owner is the responsible person under the BC Act. BCA issues PSI notices ahead of due dates; failure to comply is an offence carrying fines up to SGD 50,000.

What CVC Engineers' PSI inspection covers:

  • Visual inspection of all accessible structural elements (columns, beams, slabs, walls, roof)
  • Crack mapping with width, length, and orientation
  • Spalling, corrosion, water seepage assessment
  • Foundation settlement check (where accessible)
  • Façade attachment and curtain wall integrity
  • Roof structure and waterproofing
  • Common areas, basements, plant rooms, lift shafts
  • Photographic record (typically 100–500 images)
  • Structural condition report — written, signed, BCA-format
  • Recommendations: monitor, repair, or detailed structural investigation
  • BCA submission via CORENET-X
BCA PSI ↗ BC Act s.28 BCA PSI Manual

A real PSI defect-map sheet.

Building elevation with defects mapped — crack patterns, spalling zones, corrosion, water staining. The exact format CVC Engineers submits to BCA as part of the PSI structural condition report.

DWG · CVC-PSI-001 5-YEARLY PSI · COMMERCIAL BLDG · DEFECT MAP · ELEVATION + PLAN SCALE 1:200 REV A · 2026-05
① ELEVATION — FACE A · DEFECT MAP ② TYPICAL FLOOR PLAN · DEFECT KEY MAIN LOBBY D-01 · CRACK · 1.2mm WIDE × 4F D-02 · SPALL · 80mm DIA D-03 · RUST STAIN D-04 · WATER SEEPAGE D-05 · HONEYCOMB D-06 · LOOSE PANEL F8 RF F7 F6 F5 F4 F3 F2 F1 GF A A' A B C D E 1 2 3 D-01 D-02 D-03 D-04 D-05 D-06 CORE DEFECT REGISTER D-01 CRACK · 1.2mm × 4F (F2-F5) PRIORITY: HIGH D-02 SPALL · 80mm dia · F6/C PRIORITY: MED D-03 RUST STAIN · F3/A PRIORITY: HIGH D-04 WATER SEEPAGE · F5/D PRIORITY: MED D-05 HONEYCOMB · F3/C PRIORITY: LOW D-06 LOOSE FAÇADE PANEL · F1/D PRIORITY: HIGH ASSESSMENT — STRUCTURALLY SAFE WITH RECTIFICATION CVC ENGINEERS · PSI INSPECTION PROJECT — COMMERCIAL BLDG · 8F DUE: Q2 2026 DRAWING — DEFECT MAP · ELEV + PLAN REV B SCALE — 1:200 · ELEV / 1:300 · PLAN DATE 2026-05-10 DRN BY — CVC PE · QP-S PEB 5376 SIGNED · DATED · SEALED 2026-05-10 ✓ PSI SUBMITTED TO BCA · PASS WITH CONDITIONS
SHEET 03/12 · PSI INSPECTION REPORT PEB 5376 SEAL CHECKED · 2026-05-10 APPROVED · QP-S

PSI cost ranges.

Indicative 2026 fees for the inspection + report + BCA lodgement. Excludes BCA submission fee.

Building typeSizeIndicative fee (SGD)Notes
Landed home (residential)1–3 storey2,500 – 5,00010-yearly. Owner-occupied or rented.
HDB block (whole block)10–25 storey8,000 – 20,000Town Council appoints PE
Condo (whole development)Per block6,000 – 15,000MCST appoints PE
Small commercial / shophouse2–4 storey3,500 – 7,5005-yearly. Conservation = additional scope.
Mid-rise commercial / office5–15 storey8,000 – 18,0005-yearly. Includes lift / lobby / common areas.
Industrial / warehouseSingle block5,000 – 12,0005-yearly. Roof + truss inspection.
Heritage / conservation buildingPer building8,000 – 25,000URA conservation requirements add scope.
Detailed structural investigation (post-PSI)Per scope5,000 – 30,000+Triggered by serious defects flagged at PSI.

PSI due soon? Send the building.

Address, building type, last PSI date if known. We reply within one working day with a written PSI quote and inspection schedule.

Get a PSI quote